Skip to content

Patrick M. McGuire

Professional Engineer, Structural Engineer

April 16, 2012 Engineer-of-Record of factory built units.

Engineer-of-Record of factory built units.

Setting factory built units

This photo shows the setting in place of a third floor unit. The units were virtually complete when delivered including carpet, paint & fixtures. In the field hook ups were made for electric, plumbing, potable water & sprinklers. Once the units were set, their common walls were not accessible for structural connections. The setting sequence & interconnection method took some innovation.

at 533 × 400 in Project Gallery